Contractors
We promote the use of
Linesearch for investigating and registering new works
near pipelines.
1. All work shall be in accordance with the Guidance
Notes contained in a booklet available from BPA’s Land
and Wayleaves department. Prior to commencement of all
works a written task risk assessment and method
statement will be required. In general a legal consent
will be required prior to any works within the wayleave.
Adequate time should be allowed for the completion of
these consents.
2 No raising or lowering of ground level throughout the
easement without written consent from the pipeline
operator.
|
3 Concrete slab protection will be required over the
pipeline at permanent road crossings and parking areas.
Prior to installation the developer shall expose the
pipeline under the supervision of a representative of
the Pipeline Operator and arrange for the existing
protective pipe wrapping to be inspected, repaired and
then double wrapped at the Promoter's expense by a
contractor approved by the Pipeline Operator or his
Agent.
4 The easement shall be pegged out and fenced off prior to
works commencing. Agreed crossing points across the
easement for construction machines shall be protected by
tied timber mat, "Bog Mat" or a temporary concrete slab
or hardcore.
5 To prevent indiscriminate crossings along the
pipeline, service crossings (i.e. drains, cables, pipes,
etc.), should be grouped together at a common point.
|
These should be ducted if possible.
6 Pipeline marker posts shall be installed at the
Promoter's expense each side of all road crossings and
elsewhere as necessary, to mark the pipeline route. The
Pipeline Operator to supply markers (2 weeks notice
required).
7 No buildings, structures or caravans to be within the
pipeline easement.
8 The pipeline easement should always be in an open
area, as access to the easement and/or the pipeline is
required at all times.
9 Attention is drawn to the fact that the pipeline is
cathodically protected. This can corrode metal
structures in the vicinity and it is the Promoter's
responsibility to protect their constructions against
this.
|
10 Tree planting is restricted.
11 No explosives to be used within 400 metres (1300 ft)
of the pipeline without prior agreement with the
Pipeline Operator or his Agent.
12 No pile driving within 30 metres (100 ft) of the
pipelines without prior agreement with the Pipeline
Operator or his Agent.
13 No 3D seismic survey using the Vibrosis method
within 30 metres (100ft) of the pipeline without prior
agreement.
14 Directional drilling, thrust boring or other
trenchless techniques will be considered as an
alternative method of crossing the pipelines subject to
certain conditions being fully adhered to.
15 High voltage electric cable crossing may require
special consideration.
Visit
www.linesearch.org for further information.
|