News

BPA kicks off the Buncefield Rebuild Project

March 2013 On 27th March 2013 British Pipeline Agency Limited (BPA) began one of its biggest projects in 30 years - Buncefield Aviation Storage Terminal Rebuild Project, after its destruction in the 2005 fire. Following BPA's successful completion of the Front End Engineering Design, in 2013 BPA were instructed by West
Buncefield Rebuild

BPA repairs a pumpstation on a major UK pipeline system

January 2013 Q8Aviation appointed BPA to act as their Owner's Engineer on the project to refurbish the Royal Portbury Dock pumpstation which plays a key role in supplying aviation fuel to customers at Heathrow and other airports across the UK. BPA delivered the project without disruption to the ongoing operation
High pressure fuel pipeline repair