The Kuwait National Petroleum Company (KNPC) intends to construct a new local marketing depot at Al Matla in the north of Kuwait to meet the country’s strategic stock requirements, to cater for the demand of future population growth in the north of the country and the planned infrastructure developments. The depot needs to be connected to the existing Mina Al Ahmadi (MAA) and Shuaiba (SHU) refi neries in the south with 130km cross country pipelines (8”, 12” and 16”).

Based on its Multi-product pipeline design and operation experience, BPA was selected to conduct the pipelines FEED study to assess the route of the lines (including modifications of existing facilities as well as electrical and other auxiliary systems) and the positioning of 8 block valve stations along the pipeline route. The study included the design of the block valve sites as remotely operable standalone facilities without the need for external services (e.g. use of solar power) and with the ability to shutdown the pipeline sections when necessary to limit any potential pipeline spill. The design also included all aspects of Cathodic Protection of the pipeline.

Service
Region / Country
Value (approximate)
For more information contact:

Hemel Hempstead (Head Office)
5-7 Alexandra Road
Hemel Hempstead
Hertfordshire
HP2 5BS
UK

Tel: +44 (0)1442 242200
Fax: +44 (0)1442 214077

Related case studies

OIKIS Case Study

Pumpstation Rebuild and Pipeline Recommissioning

OIKOS Storage Limited, Pumpstation and Pipeline Following the refurbishment of their tank farm, OIKOS identified the need to recommission their 12″ pipeline for multiproduct duty and the transportation of various grades of refined petroleum products directly into the UKOP system ...
Read More
Pipe Bridge Removal BPA

Pipe Bridge Removal

UKOP/WLPS BPA manages major hydrocarbon transmission pipeline systems and bulk storage assets in the United Kingdom on behalf of their owners. We offer over 40 years of experience in setting up, operating and maintaining facilities, reducing operating costs, increasing system ...
Read More
UKOP Risk Reduction

UKOP Risk Reduction

Epping to Buncefield Pipelines This was the second phase of a project initiated in 2012 to address ‘operational risk reduction’ issues on a 40km section of the 750km UKOP multiproduct pipeline between Epping booster pumps station and the Buncefield terminal ...
Read More
Scroll to Top