Pumpstation Rebuild and Pipeline Recommissioning

OIKOS Storage Limited, Pumpstation and Pipeline

Following the refurbishment of their tank farm, OIKOS identified the need to recommission their 12″ pipeline for multiproduct duty and the transportation of various grades of refined petroleum products directly into the UKOP system from their bulk fuel storage facility in Canvey Island. The associated Pump Station had to be rebuilt at the same time. Both the pipeline and the pump station had to be commissioned by the start of the London 2012 Summer Olympics and Paralympics due to it causing increased demand for diesel and other ground fuels.

A number of design modifications were required to either end of the pipeline to allow for the launch and receipt of the inspection tool. The inspection identified areas along the pipeline requiring further work or redevelopment. This included the removal of flange connections, replacement of Cathodic Protection insulation joints, re-coating of the pipeline in areas of deterioration and re-instalment of two valves either side of the river crossing. A section of the pipeline was also partly re-built to connect the existing refurbished infrastructure and the new Pump Station.

The new Pump Station was redeveloped in a new location and BPA undertook all design and engineering works including all aspects of mechanical, civil, electrical and control and instrumentation works in order to install three new vertical can pumps, manifold arrangement, a new pig hatch, on site hydraulic system as well as cabling and instrumentation of associated pipework, valves and buildings (including new HV and LV switchgear and Control panel). Both the pipeline and the Pump Station were commissioned and put back into operation.

Service
Region / Country
Value (approximate)
For more information contact:

Hemel Hempstead (Head Office)
5-7 Alexandra Road
Hemel Hempstead
Hertfordshire
HP2 5BS
UK

Tel: +44 (0)1442 242200
Fax: +44 (0)1442 214077

Related case studies

Pipe Bridge Removal BPA

Pipe Bridge Removal

UKOP/WLPS BPA manages major hydrocarbon transmission pipeline systems and bulk storage assets in the United Kingdom on behalf of their owners. We offer over 40 years of experience in setting up, operating and maintaining facilities, reducing operating costs, increasing system ...
Read More
UKOP Risk Reduction

UKOP Risk Reduction

Epping to Buncefield Pipelines This was the second phase of a project initiated in 2012 to address ‘operational risk reduction’ issues on a 40km section of the 750km UKOP multiproduct pipeline between Epping booster pumps station and the Buncefield terminal ...
Read More
Fuel Storage COMAH

Fuel Storage COMAH Works

BAA Heathrow Airport Works were required at the Heathrow Airport fuel storage facility to meet the requirements of the COMAH Regulations (Control of Major Accident Hazards) and to enable the operator, Heathrow Airport Fuelling Company (HAFCO), to comply with its ...
Read More